2. How to send a request to the supplier

You can request your suppliers to upload Transaction Certificates (TCs) for specific Purchase Orders directly in the Certified Materials section.

📍 Step 1: Where to find it

  1. In the navigation bar, go to Traceability → Certified Materials

  2. Select one or multiple orders

  3. Click the Send request (paper plane icon) under Actions


📤 Step 2: Select orders

  • Tick the checkbox next to the PO(s) you want to request documents for

  • You can select multiple POs across the same supplier


📝 Step 3: Configure the request

In the dialog, you can configure the request details:

  1. Select assignee

    Choose a contact from the supplier company

    • Make sure the contact has a user account already set up in the system

    • Choose your contact from the supplier company

    • This specific user will receive the notification of your request

  2. Set due date

    Define a deadline for the supplier to upload the required documents

    • You can set:

      • A global due date

      • Or individual due dates per order

  3. Add a message

    Include a message to your supplier. Example: "Please provide TCs for the following POs by the due date listed below."

  4. Review selected orders

    You can review:

    • Order number

    • Applied standard (e.g. GOTS, GRS)

    • Number of PO lines

    • Quantity

    • Due date per order


📩 Step 4: Send the request

Click Send request(s) to notify the supplier.

  • The supplier will receive a notification

  • They can upload the required TC documents directly in the platform

  • The order status will change from To do In progress


✅ After sending the request

Once the request is sent:

  • You can track progress in the Certified Materials table

  • The Collected Evidence column will update once documents are uploaded

  • You can send reminders if needed

Tips & common issues

  • Ensure the supplier contact is correctly assigned

  • Always set a clear due date

  • Provide a clear message to avoid confusion

  • Group requests by supplier for efficiency